Math, asked by charlenehadyanto, 6 months ago

5 men are hired to complete a job. If one more man is hired, the job can be completed 8 days earlier. Assuming that all the men work at the same rate, how many more man should be hired so that job can be completed 28 days earlier?

Answers

Answered by PeepingMoon
11

Answer:

5 men are hired to complete a job.

If one more man is hired, the job can be completed 8 days earlier.

:

Let d = original number of days to complete the job

5d = no. of man-days required

:

when one more man is hired

6(d-8) = no. of man-days with six men

therefore

6(d-8) = 5d

6d - 48 = 5d

6d - 5d = 48

d = 48 days when 5 men are hired

5*48 = 240 man-days required to complete the job (same as 6*40)

:

Assuming that all the men work at the same rate, How many more men should be hired so that the job can be completed 28 days earlier?

Let m = no. of additional men required

(m+5)(48-28) = 240

(m+5)*20 = 240

20m + 100 = 240

20m = 240 - 100

m = 140/20

m = 7 more men for a total of 12,

:

Check by finding the man-hrs 12*20 = 240 man-hrs completes the job

:

:

It is given that z is directly proportional to x^2 and inversely proportional to sqrt%28y%29

i)Write down an equation connecting x, y and z

z+=+x%5E2%2Fsqrt%28y%29

:

ii) if z = 16 when x = 2 and y = 9

let k = the constant of variation, and write the equation:

z+=+%28kx%5E2%29%2Fsqrt%28y%29

find k

16+=+%28k2%5E2%29%2Fsqrt%289%29 = 16+=+%284k%29%2F3 = 3(16) = 4k

4k = 48

k = 48/4

k = 12

write the equation now as z+=+%2812x%5E2%29%2Fsqrt%28y%29

find the value of z when x =5 and y =4

z+=+%2812%2A5%5E2%29%2Fsqrt%284%29

z+=+%2812%2A25%29%2F2

z = 150

:

Step-by-step explanation:

Hope it helps

Please follow me✌ friend

Similar questions