5 men are working to complete a work in 15 days. After 5 days 10 women are accompanied by them to complete the work in next 5 days. If the work is to be done by women only, then in how many days could the work be over if 10 women have started it?
Answers
Answered by
0
another day started in women
Answered by
1
10 women can complete the work in 15 days.
Step-by-step explanation:
Consider the provided information.
It is given that 5 men can complete the work in 15 days.
Work done by 5 men in 1 day is:
Work done by 5 men in 10 days :
Now the remaining work is:
The remaining work completed by 10 women in 5 days .
That means work done by 10 women in 5 days is:
So work done by 10 women in 1 day is:
Hence, 10 women can complete the work in 15 days.
#Learn more
A contractor undertook to do a certain work in 75 days and employed 60 men to do it. after 25 days he found that only one-fourth of the work was done. how many more men must be employed in order that the work may be finished in time?
https://brainly.in/question/4046974
Similar questions
Chemistry,
6 months ago
Accountancy,
11 months ago