Math, asked by vasweety307, 2 months ago

5 men can do a piece of work in 12 days how many more men are required to finish the work in 6 days​

Answers

Answered by Anonymous
1

Step-by-step explanation:

No of men required to do the work in 12 days=5

No of men required to do the work in 1 day=5×12=60 men

No of men required to do the work=60/6=10 men

Answered by ashuasif2007
1

Answer:

The standard process is the following:

In 12 days it takes 5 men to finish the work.

The tricky part is the following step. Most students make a mistake here because their concept is not clear and they follow a process blindly without knowing the reasons.

As a standard practice, they would say-

“ In 1 day it takes 5/12 men to finish the work.

Thus in 6 days, it would take 5/12 * 6 = 5/2 men to finish the work.”

We see that it is actually quite impossible because 5/2 men don’t exist, but had the problem dealt with numbers which would have led to whole numbers, not fractions, they would have proceeded with the mistake.

In place of standard formula if you use some common sense then you can observe something very easily:

In 12 days it takes 5 men to finish the work.

So in 1 day, it must take 5*12 = 60 men to finish the work. Obviously to do some work in 1 day you need more manpower.

Thus to finish the work in 6 days you would require 60/6 = 10 men

Step-by-step explanation:

i hope it helps you

please mark me as brainliest

Similar questions