5 men can do a piece of work in 12 days . How many moreen should be employed to finish the work in 6 days?
Answers
Answered by
2
Answer:
By simply applying inverse of unitary method the sum can be solved.
For 5 men the work is completed in=12 days
For 1 man the no. of days taken will be more than 5men to do the same work.
1 man=5×12 days
So 5×12 days = 1man
6 days = 1 × 5× 12 /6 = 10 men.
Answered by
1
☘️ Given :
- Work done by 5 men in 12 days
- How many more should be employed to finish the work in 6 days
_____________________
☘️ Solution :
As given in the question,
5 men can finish a work in 12 days.
1 man can do it in (12 × 5) = 60 days.
So, each man can do 1/60th of the work in 1 day.
Now,
Let x be the number of men required.
Then,
work done in 1 day = x/60.
Number of days required to complete the work = 60/x.
60/x = 6, so x = 10
Thus, 10 people are required.