5 men can do a repairing work in 6 days. How many men will do in 4 days?

Direct proportion or Inverse proportion

I need it Right now

Answers

Answered by vidyadbkharat
1

Answer:

inverse proportion

Step-by-step explanation:

It is an example of an Inverse Proportion

as the numbers of days decreasing definitely we will need more mens to do the same work

Answered by ajajit9217
0

Answer:

It is an example of inverse proportion .as the number of days decreases when number of men increases.

7.5 men will do the work in 4 days

Step-by-step explanation:

In 6 days 5 men can do repairing work.

∴ In 1 day 5×6 =30 men can do the work

∴In 4 days 30/4 =7.5 men  can do the work