5 men can finish a work in 10 days how many men will finish it in 6 days
Answers
Answered by
4
5 men = 10days
? men = 6days
5×10= 50
50÷6= 8.3
Answered by
0
Answer:
12 days
Step-by-step explanation:
direct variation
5 men in 10=6 men in x days
5/10=6/x
x=10*6/5
x=60/5
x=12