5 men do any work complete in 8 days so how many times same work complete 12 mens

Answers

Answered by anjugoel114
1
we are given that 3 men take 7 days to complete the work

=> Total amount of work = 5×8= 40 man-days

We now have 12 men available with us.

Number of days required by these men to finish the work = 40/12=3.5 days (3 and half day)


Plz mark as brainliest