5 men take 20 days to complete a work working 8 hours a day. In how many days can 8 men do the same work, working 7 hours a day?

Answers

Answered by yokithasrinivasan
0

Answer:

10 days

Explanation:

5 men working 8hrs. took =20 days

1 man working 1 hr. will take= 20*5*8 days

Then, 8 men working 10 hrs. will take= ( 20*5*8 )/8∗10=10days.