5 men women finish the work of wall in 8 days how many workers added to finish the work in half a day
please answer this question
Answers
Answered by
1
Answer: 80 men women.
Step-by-step explaination:
5 people = 8 days
X people = 1/2 day
8×5 = X×1/2
40=X/2
40×2=X
X=80
80 people will complete work in 1/2 day.