5. Navjot can do a piece of work in 6 days working 10 hours per day. In how
can he do the same work if he increases his working hours by 2 hours per day
Answers
Answered by
14
Navjot working 10 hours per day can do a work in 6 days
Then, Navjot working 1 hour can do same work in 6*10 days
Then Navjot working 12 hours can do same work in 6*10/12days
= 5 days
Plz mark this answer as brainlist
Answered by
1
Let us consider the Navjot needs
6×10=60hrs to complete.
Therefore,
If he works (10+2)=12 hrs per day
Then,
12
60
=5days