5 people can do a work in 32 days in how many days 8 people can compete work
Answers
Answered by
0
Answer: 20 days
Step-by-step explanation:
Given number of people varies inversely with the number of days taken to finish the work
Then x=1/y
=>x1 *y1= x2 *y2(Note the number following the variable here is supposed to be suffix)
=>5*32=8*y2
=>160=8*y2
=> y2=160/8
=>y2=20
Therefore the number of days it take 8 people to complete the work is 20 days