5 persons can prepare an admission list in 8 days
working 7 hours a day. If 2 persons join them so
as to complete the work in 4 days, they need to
work per for
Answers
Number of people = 5
Number of hours = 7
Number of days = 8
Number of people= 7
Number of days= 4
Number of hours=?
Using the formula ,
Work1×Time1×Day1=Work2×Time2×.
Day2
5×8×7 = 7 × 4 × x
280= 28x
x= 280 / 28 = 10
Thus they would have to work 10 hours a day.
Pls mark as brainiest.
Answer:
They'll have to work 10 hours a day if they wish to complete the work in 4 days working with 7 people.
Step-by-step explanation:
This particular sum is an example of inverse proportion.
So as the number of people working increases the time that they'll need will decrease.
We are told that,
5 people complete the task in 8 days working 7hrs a day.
Therefore,
The time required = 8 × 7= 56 hrs
i.e. 5 people complete the task in 56 hrs.
Now,
With 7 people the time required = ( 5 × 56) ÷ 7 = 40hrs.
As per the given condition,
7 people complete the task in 4 days.
Therefore,
Time they will have to work for each day = 40 ÷ 4 = 10hrs per day