5 persons take 6 days to complete l/5 of their task of digging a water channel. -How
many more days will 12 persons take to finish the remaining task?
(A) 3 days (B) 6 days (C) 18 days (D) l0 days
Answers
Answered by
0
Step-by-step explanation:
i think 3 days because if 5 person can take 6 days so 12 person will take less days so 3 days i think
Similar questions