5 skilled workers can build a wall in 20days; 8 semi-skilled workers can build a wall in 25 days; 10 unskilled workers can build a wall in 30days. if a team has 2 skilled, 6 semi-skilled and 5 unskilled workers, how long will it take to build the wall?
Answers
Answered by
7
Suppose, the efficiency of skilled worker=x
The efficiency of semi-skilled workers=y and
The efficiency of unskilled workers=z
Now, according to the question, we have
5x*20=8y*25=10z*30
100x=200y=300z
x=2y=3z
divide the above equation by 6 and equate to k
x/6=y/3=z/2=k
Thus, the efficiency of skilled, semi-skilled and unskilled worker is 6:3:2.
Now, find out the total work as below:
Total work= 5x*20= 5*6*20=600
Now,
The efficiency of 2 skilled, 6 semi-skilled and 5 unskilled workers=2x+6y+5z=2*6+6*3+5*2=40
Therefore,
Time required for 2 skilled, 6 semi-skilled and 5 unskilled workers to build a wall=600/40=15 days