5. Which of the following is the 5 points
sequence of Problem solving
process in an organization
under quality management
system?
O Plan-Act-Do-Check
O Plan-check-Do-Act
O Plan-Do-Check-Act
O Plan-Act-Check-Do
Answers
Answered by
0
Answer:
plan check do act
hope it helps mark me as brainliest and follow me pls
Answered by
1
Step-by-step explanation:
may the 1 option