5 worker complete a task in 12 days how many workers required to complete the same task in 6 days?
1)15
2) 12
3) 18
4) 10
Answers
Answered by
0
Step-by-step explanation:
5×12= 6×m
m= 5×12/6= 10..
Answered by
0
Answer:
Ten workers are required.
Step-by-step explanation:
This question is based on time and work.
It is given that five workers complete a task in days.
We need to determine how many workers required to complete the same task in days.
The concept used here will be:
Hence,
Using the values here, we get
Hence, ten workers are required.