5 workers take 12 days to weed a field how many days would six workers take how many would 15 take
Answers
Answered by
2
5 workers take days = 12 6 workers will take days = 12×5/6 = 10days and 15 workers will do the work in = 12×5/15 = 60/15 = 4 days
Similar questions