50 daily workers can complete a dam project in 40 days. If 30 of them work daily and the rest work in every alternative day, how many more days will be required to complete the project.
Answers
Answered by
0
Total work= 50*40= 2000
In 40 days, daily workers complete: 30*40=1200
Alternate workers complete:20 * (40/2) = 400
Let us assume that they work for x days after 40 days.
Alternate workers will work for x/2 days.
A/Q, 2000 = 1200 + 400 + 30x + 20*(x/2)
Solving, we get x=10
Ans: 10 days
Another Approach:
Total Works: 50*40=2000
30*40=1200
20*20=400
Total =1600
1600….4/5…… 40 days
Total Works: 50*40=2000
30*40=1200
20*20=400
Total =1600
2000………. 1 work
1600…………1600/2000 work or 4/5 work
remain, 1- 4/5=1/5 work
1600….4/5…… 40 days
1600…..1……….(40*5)/4=50
1600…..1/5……..50/5 =10 days
In 40 days, daily workers complete: 30*40=1200
Alternate workers complete:20 * (40/2) = 400
Let us assume that they work for x days after 40 days.
Alternate workers will work for x/2 days.
A/Q, 2000 = 1200 + 400 + 30x + 20*(x/2)
Solving, we get x=10
Ans: 10 days
Another Approach:
Total Works: 50*40=2000
30*40=1200
20*20=400
Total =1600
1600….4/5…… 40 days
Total Works: 50*40=2000
30*40=1200
20*20=400
Total =1600
2000………. 1 work
1600…………1600/2000 work or 4/5 work
remain, 1- 4/5=1/5 work
1600….4/5…… 40 days
1600…..1……….(40*5)/4=50
1600…..1/5……..50/5 =10 days