50 labourers dig a wll in 30 days if only 40 labour are available for the work how long will the work last
Answers
Answered by
0
50/30 =0.6
0.6×40 = 24 days
0.6×40 = 24 days
Answered by
0
50 labourers dig a wall in 30 days.
1 labourers dig a wall in 30×50 days.
40 labourers dig a wall in 1500÷40days
= 75/2 days
1 labourers dig a wall in 30×50 days.
40 labourers dig a wall in 1500÷40days
= 75/2 days