50 labourers took six days to dig a pond. Use the rule of 3 to find you know in days 30 labourers could have completed the work.
Answers
Answered by
2
Answer:
50 labours complete work in 6 days
1 labour complete work in 6/50 days= 3 hour
30 labours complete work in 3*30=90 hours
hence 30 labours complete work in 3days 18hours
HOPE YOU LIKE THE ANSWER