50 men can complete a work in 65 days.Five days after started the work, 20 men left the group. In how many days can the remaining work be completed?
Select one:
a. 100 days
b. 75 days
c. Cannot be determined
d. 60 days

Answers

Answered by palneelam385
0

Answer:

75 days mark as brainliat

Answered by pmd43638
0

Step-by-step explanation:

75 days.....

I hope helpful for you please mark as a brainlist answer and follow me.....