50 persons can do a piece of work in 18 days.in how many days can the same piece of work be done by 75 persons?
Answers
Answered by
25
12 days
Step-by-step explanation:
Given,50 persons can complete a piece of work in 18 days
⇒1 person can complete a piece of work= 18×50
⇒75 person can complete a piece of work=
=12 days
Answered by
8
Answer:
50 person can complete a piece of work in 18 days
=1 person can complete a piece of work in 18×50
75 person can complete a piece of work in 18×50/75
12days