50. Ramu can finish the work in 10 days. Ravi can
do the same work in 15 days. Then in how
many days Ramu and Ravi finish the work?
(A) 5
(B) 7
(C) 8
(D) 6​

Answers

Answered by aditikanwadkar
1

Answer:

A) 5

Mark me Brainliest!!

Answered by asahilthakur
1

Answer:

(D) 6

Step-by-step explanation:

Work done by Ramu in 1 day = 1/10

Work done by Ravi in 1 day = 1/15

Work done by both in 1 day = 1/10 + 1/15 = (3+2) / 30 = 5/30 = 1/6

Hence, Ramu and Ravi will finish the work in 6 days.