50. Ramu can finish the work in 10 days. Ravi can
do the same work in 15 days. Then in how
many days Ramu and Ravi finish the work?
(A) 5
(B) 7
(C) 8
(D) 6
Answers
Answered by
1
Answer:
A) 5
Mark me Brainliest!!
Answered by
1
Answer:
(D) 6
Step-by-step explanation:
Work done by Ramu in 1 day = 1/10
Work done by Ravi in 1 day = 1/15
Work done by both in 1 day = 1/10 + 1/15 = (3+2) / 30 = 5/30 = 1/6
Hence, Ramu and Ravi will finish the work in 6 days.