50 workers can complete a piece of work in 40 days, all workers start the work but after every 10 days 5 workers left the work then in row many days total work will be completed?​

Answers

Answered by Nitingenius205
0

Answer:

if the work is completed then why they will do the same work again

Answered by srabanisaha19
0

Answer:

workers. days

50. 40-10=30

50-5=45.

50 workers complete the work in 30 days.

1 workers com the work in 30÷50

45. ". ". 30÷50×45=27 days

therefore 27 days total work will be completed.

I hope this is the ans.