50 workers can complete laying the tiles of a mall in 10 days how many additional worker are required if after 3 days it is decided that the work must be completed in 8 days instead of 10 days
Answers
Answered by
1
50 workers can complete laying the tiles of a mall in 10 days how many additional worker are required if after 3 days it is decided that the work must be completed in 8 days instead of 10 days
Step-by-step explanation:
number of workers = 50
Number of days required by 50 workers = 10
Let the number of workers who will complete the work in 8 days be y
inverse variation:
50*10= y*8
8y= 500
y= 500/8
y= 125/2
y= 62.5
The Additional workers will be given by = 62.5-50
=12.5
The number of additional workers is 13