Math, asked by kkanchandevi1388, 7 months ago

50 workers can complete laying the tiles of a mall in 10 days. How many additional workers are te
after 3 days it is decided that the work must be completed in 8 days instead of 10 days?
Chailenge
(d) 5
(b) 10
(c) 20​

Answers

Answered by arhamsethia3108
0

Plz mark my answer as the brainliest one

Step-by-step explanation:

C) 20 workers would be needed

Answered by tripti5718
0

Answer:

20

hey buddy I suggest you 20

As I think it's the right answer

sorry if incorrect