50 workers can complete link the tiles of a wall in 10 days how many additional workers are required if after 3 days it is decided that the work must be completed in 8 days instead of 10 days​

Answers

Answered by RadhikaParwal
1

Answer:

no. of workers= 50

No. of days required by 50 workers= 10

Let the no. of workers who will complete the work in 8 days be x

As there is inverse variation,

50*10= x*8

8x= 500

x= 500/8

x= 125/2

x= 62.5

Additional workers= 62.5-50

=12.5

the no. of additional workers required is 13(approx)