500 persons completed the building in 25 days how many persons will be needed to complete the same building in 10 days

Answers

Answered by akchita124pekc5c
5
25days=500persons
1days=500×25 persons
10days=500×25/10=1250persons

hope this may help you

rajiv4467: I'm very very thankful to you
Answered by manlegend544
0

Answer:

1250 persons

Step-by-step explanation:

days=25 , 10

persons=500 , x

500×25=10x

x=12500÷10

x=1250