500 persons completed the building in 25 days how many persons will be needed to complete the same building in 10 days
Answers
Answered by
5
25days=500persons
1days=500×25 persons
10days=500×25/10=1250persons
hope this may help you
1days=500×25 persons
10days=500×25/10=1250persons
hope this may help you
rajiv4467:
I'm very very thankful to you
Answered by
0
Answer:
1250 persons
Step-by-step explanation:
days=25 , 10
persons=500 , x
500×25=10x
x=12500÷10
x=1250