5000 workers need 40 days to complete a work then how many days will 8000 workers need
Answers
Answered by
0
Step-by-step explanation:
5000 workers --40 days
1 worker --- 40/5000 days
8000 workers --- 40/5000*8000
8000 workers ---64 days
They will need 64 days to complete the work.