51. A certain number of men com-
plete a piece of work in 60 days.
If there were 8 men more, the
work could be finished in 10 days
less. How many men
many men were
originally there?
(A) 30
(B) 40
(C) 32
(D) 36
Answers
Answered by
0
answer
B) 40
Step-by-step explanation:
we are asked to find out the no. of workers there were at the beginning .
Let the no. of worker be x. Now we can calculate the total work algebraically.
60*x = total work.
but if there were 8 more men this task could be performed 10 days early. It means we could do the task in 50 days.
(x + 8) = total no. of men
So, 50(x + 8) = total work.
60x = 50(x + 8)
x = 40.
the best answer is B
please mark as brilliant !