52. P can complete a work in 12
days working 8 hours a day,
can complete the same work in
8 days working 10 hours a day.
If both P and Q work together,
working 8 hours a day, in how
many days can they complete
the work?
Answers
Answered by
2
P takes 12 days to complete a work working 8hr per day,
P can complete work in 12days×8hr/day=96hr...
similarly,
Q completes work in 8×10=80hr....
P's 1hour work =1/96
Q's 1hour work =1/80..hence
(P+Q)'s 1hour work=[(1/96)+(1/80)]
=11/480
so,(P+Q) together can complete work in 480/11 hours...
given (P+Q) work 8hr per day..
1day-------------------->8hr they work
'x'days-----------------> (480/11)hr
on cross multiplication,
x=60/11days
=5 5/11 days