Math, asked by sawansraut2006, 11 months ago

550 people can complete a work in 100 days.After 10 days start of work 50 more people jion.In how more days now will be completed?

Answers

Answered by lubna165
0

Step-by-step explanation:

550 people complete work in 100 day

1 people complete work in 100×550 days

If 50 more people is added then total number of people =600 people

After ten days number of days left =90

600 people complete work in 90 ×550/600

=82 days