Math, asked by abhisfjk, 1 year ago

550 people can complete a work in 100days.After 10 days start of the work 50 more people join.In how many more days now the work will completed

Answers

Answered by TooFree
6

550 people can do the work in 100 days

⇒ 1 day = 1/100 of the work


Amount of work completed by 550 people in 10 days:

1 day = 1/100

10days = 1/100 x 10 = 10/100 = 1/10 of the work


Amount of work left to do after the 10 days:

Amount of work left = 1 - 1/10 = 9/10 of the work


------------------------------------------------------------------------

Number of people after 50 joined in:

550 + 50 = 600 people


Find the number of days needed for 600 people to complete the work:

550 people = 100 days

1 person = 100 x 550 = 55000 days

600 people = 55000 ÷ 600 = 275/3 days


Find the number of days needed to complete the rest of the work:

Rest of the work = 9/10 of the work

whole work =  275/3 days

9/10 of the work = 9/10 x 275/3  = 82.5 days


Answer: They need another 82.5 days