56 labours can do a piece of work in
8 days. If the work is completed in 7.
days, then how many more labours are
needed to finish the whole work?
Answers
Answered by
7
Answer:
The answer is 64 days.
Step-by-step explanation:
GOOD MORNING
To complete the work with 8 labours 56 days are needed
To complete the work with 1 labours (8×56) days are needed
SO, The work will be completed in {(56×8)÷7} days with 7 labours
{(56×8)÷7}={448÷7}
=64
So the answer is 64 days
Similar questions