56 workers can construct a house in 48 days. How many more workers are needed to the construct the house in 42 days?
Answers
Answered by
3
Answer:
49 workers are needed
Step-by-step explanation:
in 48 days workers are = 56
in 1 day= 56/48
in 42 days= 56/48×42
ans=49
Answered by
1
Answer:
Total no of workers (x1) =56
No of days (y1) =48
since, x1/y1 =x2/y2
56/48=x1/42
56*42/48=x
x=49