56 workers can reap a field in 8 days if the work is to be completed im 7 days
Answers
Answered by
8
Given,
In 8 days, field is reap by = 56 workers
In 1 day, field is reap by = 56/8
= 7 workers
In 7 days, field is reap by = 7*7
49 workers
In 8 days, field is reap by = 56 workers
In 1 day, field is reap by = 56/8
= 7 workers
In 7 days, field is reap by = 7*7
49 workers