560 labourers can complete a work in 9 months How many extra men should to be employed to complete the work in 7 months
Answers
Answered by
0
Step-by-step explanation:
9x520=7x12 (T1xI1=7x12)
12=9*520/7
I2=668
Therefore,520–668=148Ans
148 mens required