5person can finish a certain work with n 4 days how many person are needed to finish it in 2 days
Answers
Answered by
0
To do the job in 2 days u need an unknown number for the person,I'll number it as p
p x 2 days = 20 people days
p = 10 people
using 10 people u can do the job in 10 days
answer= 10 days checking if it's correct plugging
p in equation p x 2= 20
hope it's helpful (θ‿θ)