Math, asked by mastergreat232janvi, 5 months ago


6. 12 men working 8 hours a day, complete a piece of work in 10 days. To complete the same work in 8
days, working 15 hours a day, the number of men required is
(a) 4
O (6)5 5
O (c) 6
o (d 8​

Answers

Answered by Rumanshadowofthunder
1

Answer:

hi how r u (c ) hi

Step-by-step explanation:

Iam Ruman

Answered by Anonymous
5

Working 8 hrs in a day men needed =12

⇒ Working 1 hr in 1 day men needed =12×8×10

⇒ Working 15 hrs in 8 days men needed =

15×8

12×8×10

=8

∴ Men needed =8.

Hence, the answer is 8.

Similar questions