Math, asked by prabhat4969, 11 months ago

6. A and B can do a piece of work in 72 days. B
and C in 120 days and A and C in 90 days. In
what time can A alone do it?
(A) 60 days
(B) 120 days
(C) 110 days (D) 55 days​

Answers

Answered by yadavrai93
0

Answer:The answer is 110 days.

Step-by-step explanation:

A+b=72-@1

B+C=120-@2

C+A=90-@3

Now you can easy solve it by these equations

Answered by neelroxx2001
2

Answer:

(B) 120 days

Step-by-step explanation:

Let A take x days, B take y days and C take z days to complete the work alone.

Thus, Work done by A in 1 day = 1/x

Work done by B in 1 day = 1/y

Work done by C in 1 day = 1/z.

Work done by A and B together in one day = 1/x + 1/y

Work done by B and C together in one day = 1/y + 1/z

Work done by A and C together in one day = 1/z + 1/x

Thus, time taken by A and B to together complete the work = \frac{1}{1/x+1/y}

Also, time taken by B and C to together complete the work = \frac{1}{1/y+1/z}

Also, time taken by C and A to together complete the work = \frac{1}{1/x+1/z}

By the given conditions,

\frac{1}{1/x+1/y} = 72

\frac{1}{1/y+1/z} = 120

\frac{1}{1/x+1/z} = 90

or  1/x + 1/y = 1/72 .....................( 1 )

     1/y + 1/z = 1/120 ...................( 2 )

     1/z + 1/x = 1/90 .....................( 3 )

Subtracting equation ( 2 ) from equation ( 3 ),

1/x - 1/y = 1/90 - 1/120

or 1/x - 1/y = 1/360 -----------( 4 )

Adding equations ( 1 ) and ( 4 ),

2/x = 1/72 + 1/360

or 2/x = 1/60

or x = 120.

Thus, A can finish the work alone in 120 days.

Option (B) is correct

Hope it helped you.

Do mark this answer as the brainliest.

Follow me to get all your maths doubts cleared

Similar questions