A and B working together can do a piece of work in 12 days, while B alone can
finish the work in 30 days. In how many days can A alone finish the work ?
Answers
Answered by
1
A and B finish the work in 12 days
so,A+B=12
and,B finish work alone in 30 days
B=30
then A=B-[A+B]
=30-12
=18