Math, asked by gopaldas16081987, 19 days ago

6. A can do a work in 12 days and B can do the same work in 4 days. They work together
only for 1 day and then B leaves the work. In how many days will A complete the
remaining work?​

Answers

Answered by xboy4949
2

Answer:

8 days

Step-by-step explanation:

Efficiency of A = 1/12

Efficiency of B = 1/4

Working together,

Total Efficiency

= A's efficiency + B's efficiency

= 1/12 + 1/4

=1/3

it means that working together they both would complete the 1/3 of work.

The remaining work = 1 - 1/3 = 2/3

which will be done by A alone,

Days to complete it = 12 × 2/3 = 8 Days