6 boys can complete a work in 17 days.1 boy can comlete it in

Answers

Answered by AFFAN16
0
1 boy can complete it in 2.83 days

lathahemaraja: explain breiefly
AFFAN16: simple Divide 17 by 6
lathahemaraja: briefly
lathahemaraja: but the answer is not in the option
AFFAN16: what are the options can u tell me
lathahemaraja: 102,119,85,136
AFFAN16: can u send me the image
AFFAN16: the option can't be this
AFFAN16: sorry the answer is 102
DDhanush: the answer is not 2.83 days answer is 102
Answered by Anonymous
0
The answer is 6*17=102.

AFFAN16: but why multipy
Anonymous: one boy's 17 days work is 1/6 so one boy's one day's work will be 1/(17*6)
Anonymous: one boy's whole work will be completed in 17*6 or 102 days