Math, asked by prasharti, 1 year ago

6 boys can complete the work in 16 days. 1 boy can complete it in

Answers

Answered by iammrmitulp7n6ud
11
6 Boys can complete work in 16 days

Means in 1 day 6 boys can do 1/16 of the work

In 1 day 1 boy can do 1/6 x 1/16 of the work
= 1/96 of the work

So he can complete the work in 96 days
Answered by cynthiarai
1
here's the solution
Attachments:

iammrmitulp7n6ud: how can ans be 8/3...... do u mean one boy can do it 6 times faster than 6 boys together
cynthiarai: it is unitary method
iammrmitulp7n6ud: see that cant be applicable here as it is inversely proportional question not directly proportional.......
cynthiarai: ok