6. Find the cost of levelling a badminton court 132 m long and 58 m broad at the rate of 80 per sq. m. If its length is 22 m, find​

Answers

Answered by FleurxExotica
19

Given :-

Length of the badminton court = 132 m

Breadth of the badminton court = 58 m

\\

To Find :-

Here, we have to find the rate of levelling the badminton court.

\\

Solution :-

To find the cost of levelling the badminton court, firstly, we have to find the area of the badminton court; And, we know that,

  • Area of Badminton Court = Length × Breadth
  • Area of Badminton Court = 132 m × 58 m
  • Area of Badminton Court = 7656 m².

Now, to find the cost of levelling the badminton court, we will multiply area of badminton court to the cost of levelling on one metre square area;

  • Cost of levelling the badminton court = 7656 m² × Rs. 80
  • Cost of levelling the badminton court = Rs. 612480.
Answered by prachibarapatre
8

"Although there is a mistake in your question, you might be referring to this full question: Find the cost of leveling a badminton court 132 m long and 58 m broad at the rate of 80 per sq. m."

length = 132 m

breadth = 58 m

First, we will find the area of the badminton court

Area of badminton court = 132 × 58

                                         = 7656 m²

Now, it is given that the rate of leveling is 80 per sq m

Therefore, cost of leveling = 7656 × 80

                                             = Rs. 612480

Hence, the cost of leveling the badminton ground will be Rs. 612480