6. 'क' तथा 'ख' किसी काम को 4 दिन में करते हैं. यदि 'क,
अकेले उसे 6 दिन में करता है तो 'ख' अंकले उसे कितने दिन
में पूरा
करेगा?
(A) 10 दिन
(C) 16 दिन
(B) 12 दिन
(D) 20 दिन
Answers
Answered by
1
Answer:
12 days
Step-by-step explanation:
work can be done by A in 1 day = 1/6
work can be done by A and B together = 1/4
let,
work can be done by B in 1 day =1/x
1/6 +1/x =1/4
1/x = 1/4 - 1/6
1/x = 6-4 / 24
1/x = 2 / 24
1/x = 1/12
x=12
hence B can do work in 12 days.
Answered by
0
Answer:
raat me milna kabhi bata denge
how to s3x...besharam
Step-by-step explanation:
AB is the straight line
∠AOQ+∠BOQ=180
o
∠BOQ=180
o
−58
∠BOQ=122
o
In triangle BOQ,OB+OQ are equal since they are radius of the circle (OB=OQ)
So ∠OBQ=∠OQB (Since sides opposite are equal angle opposite to the equal sides are equal)
So ∠OBQ+∠OQB+∠BOQ=180
o
122
o
+2(∠OBQ)=180
o
→∠OBW=29
o
In triangle ABT⇒∠ABT+∠BAT+∠BTA=180
o
=29
o
+90
o
+∠BAT=180
o
∠ATQ=61
o
Similar questions
Math,
1 month ago
Physics,
1 month ago
Computer Science,
1 month ago
Social Sciences,
3 months ago
Math,
3 months ago
History,
10 months ago
Physics,
10 months ago