6 man can do a piece of work in 5 days in how many day 10 Man do it
Answers
Answered by
45
Given :-
- 6 men can do a piece of work in 5 days
Solution :-
Sam work done by 10 members in how many days ?
→ 6 men = 5days
→ 10 men = ? = x
By cross multiplication,
=> 6(x) = 50
=> x = 50/6
=> Work done by 10 men (x) = 50/6 = 8.3 days
Answered by
12
Given :
- 6 man do a piece of work in 5 days
To Find
- In how many days 10 man can finish piece of work
Solution :
Let the required number of days be x
So We know that
- Man = 6 , Days = 5
- Man = 10 , Days = x days
______________________________________
Explanation :
By inverse variation
➡ 10 : 6 = x : 5
➡ 10 / 6 = x / 5
➡ 6 × x = 10 × 5
➡ x = 10 × 5 / 6
➡ x = 50 / 6
- ➡ x = 25 /3
Therefore,
So 10 man can finish piece of work in