6 man can do a work in 7 days then in how many days 21 man can do work
Answers
Answered by
0
Answer:
3.3
Step-by-step explanation:
may be it will be useful for you
Answered by
1
Step-by-step explanation:
x= men req. y= hrs req.
Hence; x*y=k ……. Where k is const.
To find k …put x=6; y=7…..(given)
Hence we get; k=6*7=42
For x=21; 21*y=42
We get y=2
Hence, no. Of days days required for 21 men to complete the task is 2.