6 men and 8 boys complete a work in 10 day and 26 men and 48 boys complete same eork in 2 days
Answers
Answered by
1
Let M denotes the work done by a man in 1 day and B denotes the work done by a boy in 1 day.
Now, 6 men and 8 boys do the work in 10 days means 10(6M+8B) = 1
Similarly, 26 men and 48 boys do the work in 2 days means 2(26M+48B) = 1
=> 10(6M+8B) = 2(26M+48B)
=> 60M + 80B = 52M + 96B
=> 8M = 16B
=> 1M = 2B
Thus, if we employ 15 men and 20 boys, we mean to say; 15M + 20B
= 30B + 20B = 50B.
Now, (6M + 8B) do the work in 10 days.
=> (12B + 8B) do the work in 10 days.
=> 20B do the work in 10 days.
=> 1B do the work in 10×20 = 200 days.
=> 50B will do the work in 200/50 = 4 days