Math, asked by arishavashu61417, 8 months ago

6 men build a wall in 5 days . If 4 more men are employed, find the number of days in which the wall will be built

Answers

Answered by kartikgoyal007
5

Step-by-step explanation:

6:5 :: 10:X

therefore

6x=50

X=50/6

X= 25/3 days

=8 1/3 days